DilliC and ITIL 4 change enablement: a map for auditors

Draft of 1 November 2026. Last updated 23 November 2026.

This document maps DilliC to ITIL 4's change enablement practice, element by element, and then to the practices change enablement works with, one by one. It is written for the person who must say whether an organisation's change control, run in DilliC, does what ITIL 4 asks. Each row says what ITIL asks for, what DilliC does, where on the screen to see it, and what record stands as evidence. The last section is a walk through a live account that an auditor can tick along.

Three words grade every row, the same three the security questionnaire uses. Yes: DilliC does it and keeps a record. In part: DilliC does some of it, and the row says which part the organisation supplies by procedure. No: DilliC does not do it; the organisation does it elsewhere.

ITIL is a registered trade mark of PeopleCert. DilliC is not certified against ITIL, and this map is our own reading of the ITIL 4 practice guides against the product as it is today. It is written from the user guide and the code, and the chapter numbers refer to the user guide. Where a feature depends on a module, the row says so; the organisation turns modules on under Administration → Modules.

1. Where change enablement lives in DilliC

A change request is DilliC's change record: permission to put work live, kept apart from the work itself. A story is how work is broken down; a change request is the control around releasing it. One change request usually authorises several versions, and each version carries work items. A deployment is what the pipeline reports happened, and DilliC walks from the deployment back through the version to the change request to answer "on whose authority did this go out". Nothing in that chain is declared by hand: a screen cannot say that work reached production, only a pipeline can.

The screens: Delivery → Release path holds versions, change requests and deployments; Delivery → Calendar draws the change schedule; Delivery → Services holds the configuration items. The policy sits under Administration → Workflow & approvals (the change workflow, the risk questionnaire, the routing rules and the approval gates) and Administration → Environments. The figures are in Reports → Change requests. Change enablement needs the Change management module, and gates need Approvals.

2. The practice, element by element

ITIL 4 states the practice's purpose as maximising the number of successful service and product changes by ensuring that risks are properly assessed, authorising changes to proceed, and managing the change schedule. The table takes the practice guide's elements in turn.

ITIL 4 asks for DilliC does Where Evidence Status
A change record for every change, with its type, risk, impact, plans, schedule and outcome. A change request with a reference (CHG-0001), title, description, type, risk, impact, implementation plan, rollback plan, test plan, planned and actual window in a named time zone, the services it touches, the versions it authorises, an outcome and review notes. Delivery → Release path → Change requests → Raise a change request; chapter 9. The change's page; its event history; the export. Yes
Three change types: standard (pre-authorised, low risk, well understood), normal (assessed and authorised), emergency (expedited). Type is Standard, Normal or Emergency. A standard change may go straight from New to Scheduled; any other type is refused that move and must pass the authority. Emergency changes follow the same lifecycle unless a routing rule or a freeze treats them apart. Type on the change; the Move it buttons. The type on the record; change_request.transitioned events. Yes
Change models: a repeatable way of handling a kind of change, with its own assessment and authority. A library of change models, each with its plans, the services it touches, its answers to the risk questionnaire, a notice to the people it lands on, and its type, offered on the whole organisation or on one part and beneath. A change raised from a model is filled from it where the person raising it left room, scored by its answers, and names the model it came from. A standard model is the pre-authorisation: a change raised from it takes the standard path and skips the authority. Routing rules choose the authority for the rest by risk and type. A model a change was raised from is retired rather than dropped. Administration → Workflow & approvals → Change models, Risk assessment, Which authority, by risk; Start from a model on the raise form; chapter 17. The library; change_model.added, change_model.edited, change_model.retired; the model named on each change and in its history. Yes
Risk and impact assessment before authorisation. A questionnaire scores risk and impact apart. Seven questions ship (rehearsed before, tested like production, time to roll back, services touched, who notices, data or money touched, critical service's window) and the organisation rewrites them. Under a third of the points is low, under two thirds medium, the rest high. A level set by hand overrides the score, and the record says who did and what the questionnaire had scored. Assessment on the change; Administration → Workflow & approvals → Risk assessment. The answers and scored levels on the record; change_request.assessed and change_request.levels_set; the override's name and time. Yes
A change authority matched to the change's risk, with recorded decisions. Routing rules send each risk level, and optionally each type, through a named approval gate or through none. The shipped gate is the Change Advisory Board: two leaders, not the requester. A gate names who decides (a role, or anyone with the right), how many approvals it needs, and whether the author may be one. Each person decides once; one rejection ends the request; administrators may always decide. Administration → Workflow & approvals → Approval gates and Which authority, by risk; Mine to approve on the change list. Each approval decision: person, verdict, comment, time. The gate's definition. Yes
Authorisation only of a defined, planned change. A change cannot be submitted while work it releases is unfinished, and cannot reach the authority without both an implementation plan and a rollback plan. Once submitted, work cannot move in or out of its versions without withdrawing it. Enforced on Submit for authorisation. The refusal message; change_request.work_moved_out when work is removed with a reason. Yes
A change schedule: planned changes visible together, conflicts found, freezes respected, the schedule communicated. The calendar draws six weeks of change windows as bars among the sprints, with freezes shaded behind and who is away written into the days. A change is warned when it collides, another live change in an overlapping window touches the same service or one a dependency away, or falls inside a freeze that does not exempt its type. The same warning sits above the approval on the change's page. A warning is never a refusal. Delivery → Calendar; chapter 9. The calendar; the warning on the change, which the approver reads before deciding. Yes
Change freezes. A freeze has a name, a reason, a window with its time zone, whether emergency changes may go ahead, and a scope: one part of the organisation or the whole. Declaring and lifting one is a right. Delivery → Calendar → Declare a freeze. The freeze record; the warning on changes inside it. Yes
Realisation control: the change is implemented as planned, in its window. Begin implementation and Implementation complete stamp the actual start and end, which can also be taken from what the deployments did. The planned window stays beside the actual one. Set the window; the Implementation status. Planned and actual times on the record; change_request.window_observed when the actual window is taken from the deployments. Yes
Authorisation reconciled with what was deployed. Each environment is Not asked, Recorded or Gated. Recorded flags an arrival no authorised change covers. Gated holds a pipeline that asks the deployment check until a change authorises the work; a pipeline that does not ask is let through and its arrival is recorded as a bypass. An emergency change authorised after the fact reads as authorised but not in advance. Administration → Environments; Delivery → Release path → Deployments; chapter 21. Events deployment.reached, deployment.arrived, deployment.unauthorised, deployment.bypassed, deployment.held, each also posted to subscribed webhooks. Yes
Post-implementation review and closure. At review, Record outcome: successful, successful with issues, failed, or rolled back, with what happened. The incidents the change caused and the problems it fixed are listed on it. Closed is final; the record archives itself two weeks after the outcome is recorded, kept and searchable. Record outcome; Consequences on the change. change_request.reviewed; the outcome and notes; change_request.archived. Yes
Rework and cancellation without losing the record. A change can be sent back from authorisation, cancelled from any status, and reopened from cancelled but never from closed. Move it. change_request.transitioned with the note to the authority. Yes
Measurement of the practice: success and failure rates, lead time, emergency share, incidents caused. The Change requests report, over 30, 90 or 180 days: changes implemented, success rate, change failure rate, share that were emergencies, median lead time from raising to done, incidents caused, and deployments to production per week, by month and by service, with every change as a row. Change failure rate and deployments per week are the DORA pair. Reports → Change requests; chapter 11. The report; its rows; the service's twelve-month health figures. Yes
A full history of each change: who did what, when. Every action on a change writes an event with its actor and time: raised, updated, assessed, levels set, transitioned, version linked or unlinked, window observed, work moved out, reviewed, archived, restored. Approval decisions are kept apart with the decider's comment. Nothing on the trail is edited. The change's page. The event list; the export of the whole account. Yes
Communication of changes to those affected. A change carries a notice to the people it lands on, and announcing it lists it, with its window, services and notice, on the service desk's portal and on the page of each service it touches until a week after its window ends. Its plans and assessment stay inside. Every person has a calendar feed of the change windows and freezes they may read, for Outlook, Google or Apple. A SEV1 or SEV2 incident on a service notifies the service's owner. Outbound webhooks post change and deployment events, change_request.announced among them. People watching an item are notified of its moves. Notice to the people it lands on on the change; the portal; a service's page; Subscribe in your calendar on the calendar; Administration → Connections → Outbound webhooks. change_request.announced; the portal and the feed; webhook deliveries; notifications. Yes

3. The practices change enablement works with

ITIL 4 describes change enablement inside value streams with other practices. For each, the table says what DilliC supplies to the joint work and what it does not.

Service management practices

Practice ITIL 4 asks for DilliC does Where Status
Release management Releases planned, their contents known, and their authorisation traceable. A version has a name, a due date and notes. Work is aimed at it, and only work not on another live version is offered. Releasing says what shipped, slipped and was dropped. The release path shows each version's state, how far it has reached along the environments, and the change requests that authorise it, with a warning when work went out under none. Delivery → Release path → Versions; chapter 9. Yes
Deployment management Deployments recorded, by environment, tied to what they carried. The pipeline reports each deployment with its environment, versions, change requests and items. Environments are ordered along the path to production, and an environment the pipeline names that is not listed is added. Nobody records a deployment by hand. Delivery → Release path → Deployments; Administration → Environments; Administration → Connections → Version control & CI. Yes
Service configuration management Configuration items with owners, criticality and relationships, used by other practices. A service has a kind (application, infrastructure, platform, business service), a criticality, an owner, the entity that answers for it, what it is part of, what it depends on, and a stage (planned, live, retired). Changes, requests and incidents name the services they touch. A factor, an assessment, an initiative and a risk may belong to one service, whose page shows that plan, and a service may carry a weight among the services its entity runs. An inventory reported by a cloud account, a Kubernetes cluster or a Terraform state waits to be accepted as services, and a service says where it was found, when it was last seen and when it stopped being reported. DilliC scans nothing itself, keeps a dozen reported facts for each asset, and keeps no history of attribute changes. Delivery → Services; chapter 9. In part
Incident management Incidents recorded with severity and timing, linked to cause and to service. An incident carries a severity (SEV1 to SEV4), when it started, the services that went down, the change that caused it (offered from changes implemented against those services in the prior three days), and the problem it sits under. Raised on the desk or from the change that caused it. Needs the Service desk module. Service desk; chapter 9. Yes
Problem management Problems with root cause and known error, linked to incidents and to the change that fixes them. A problem carries a root cause, a known error, the incidents under it, and the change it is fixed by. The change lists the problems it was raised to fix. Service desk; chapter 9. Yes
Service desk A single point of contact with queues, routing and the record of each request. Queues with a public portal and an email address each, categories, assignment (manual, round robin, least loaded), working hours, canned replies and arrival rules. Requesters need no account. Service desk tab; appendix D. Yes
Service request management Requests fulfilled against agreed times. Each queue promises reply and resolve times, by priority where wanted, stamped onto the request when raised; the clocks count working minutes. The Service desk report says how often the promises were kept. Service desk → Queues; Reports → Service desk. Yes
Service level management Agreed service levels, measured and reported. The queue promises above, and the ten service health figures a month at a time for twelve months, hours to first response among them, each readable as a KPI with a target. No customer-facing SLA document is produced. Queues; a service's page. In part
Service validation and testing Changes tested before release, with evidence. A test plan on every change, a risk question on whether it was tested somewhere like production, and CI pipelines connected so deployments to test environments are recorded. Test results themselves are not held. The change; Administration → Environments. In part
Monitoring and event management Events detected and acted on. Alerts from a monitor arrive by webhook and raise and resolve incidents: Grafana's and PagerDuty's webhooks as they send them, or DilliC's own shape from any other sender, another service desk included. The same alert firing again is a line on the incident it raised. A SEV1 or SEV2 incident pages the escalation policy of its service or its queue: whoever is on call for a rota, then the next step, until somebody acknowledges. DilliC detects nothing itself, and pages by email, chat and the phone app, not by telephone call or text message. Administration → Connections → Alerts in; the desk, On call. The sources and when each last posted; the incidents they raised.
Availability management Availability measured and improved. Availability per service per month: the share of the month with no SEV1 or SEV2 incident open, overlapping incidents counted once. A KPI read from it takes a target like any other, and a factor or initiative is judged by it; hours to restore and incident counts sit beside it. Availability is read from the incidents people raise, not from a probe: an outage nobody reported is not counted. A service's page; Administration → Measures/KPIs. Yes
Service catalogue management A catalogue of services and of what may be requested. The services list is the technical catalogue; the queues on the portal are the request catalogue. Neither is published as a document. Delivery → Services; the portal. In part
Business analysis, capacity and performance, service continuity, IT asset management, service design — Not addressed, except that factors and assessments (chapter 5 and 6) do some of business analysis's work in planning. — No

General management practices

Practice ITIL 4 asks for DilliC does Where Status
Continual improvement Improvement opportunities identified, measured and tracked to outcome. The planning half: factors and objectives, assessed by survey into a matrix; root cause analysis with assertions, causes and evidence cited from the desk's incidents and problems; initiatives linked to the root causes they answer and the objectives they serve; and a Benefits tab that says whether each initiative is adopted and effective. Needs the Planning module. Strategic planning; Assessments; Root cause analysis; chapter 5 to 8. Yes
Risk management Risks identified, owned and treated. Change risk is scored per change. Delivery risks are raised against a team with likelihood and impact, placed on a matrix, and answered the ROAM way: resolved, owned, accepted, mitigated. The register reads at any level of the organisation: a division's is every team's risks beneath it, each with its ROAM answer and whose it is, the worst rated first. Delivery → Risks & dependencies, scope This entity and everything beneath it; the change's assessment. Yes
Knowledge management Knowledge captured, kept current and reused. Pages: a wiki with versions, a page per initiative and epic, the Article template (Symptoms, Cause, Fix, Applies to), pages handed to requesters on the portal with counts of who said they helped, and a review date on pages the desk writes. Needs the Pages module. Pages tab; chapter 9. Yes
Measurement and reporting Metrics defined once, read consistently, reported. A measure/KPI library with units, ranges and roll-up rules; readings typed in or read from six desk and change figures; dashboards answered live for each reader; five shipped reports; the query language. Administration → Measures/KPIs; Dashboards; Reports; chapter 11 and 19. Yes
Organisational change management The people side of change: stakeholders, readiness, communication, resistance, adoption. The Adoption module, initiative by initiative: stakeholder groups on an influence and support grid with the impact on each; readiness rounds surveying awareness, desire, knowledge, ability and reinforcement; a communications and training plan; a resistance log; adoption targets; a saturation heatmap. Adoption tab; chapter 8. Yes
Portfolio management Investments chosen and funded against capacity. A portfolio kanban with a hypothesis and lean business case per epic, WSJF ranking, a funding gate (two approvers, not the proposer), and value streams with budgets and soft or hard guardrails. Needs the Portfolio module. Portfolio; chapter 10. Yes
Service financial management Costs of change and of services known. Budget, commitments, actuals and forecasts per initiative, with the finance system's reference on each line; labour derived from hours and a cost per hour; child initiatives checked against the parent's budget. Spend by service is read from the initiatives that establish, enhance or retire it: each one's budget, commitments and actuals on the service's page, totalled where they share a currency, and what has been committed and spent in the services list. No costing of a service beyond that: running costs, licences and shared infrastructure are not apportioned to it. An initiative's Spend tab; a service's page; chapter 8. In part
Project management Work planned, scheduled and tracked to delivery. Initiatives with budgets and measures, broken into epics and stories; boards, sprints, timeline and roadmap; velocity, cycle time and flow. No critical path or resource levelling. Delivery; chapter 9. In part
Information security management Security controls in the change process and in the tool. A gate can be a security review on any move. The tool itself: single sign-on, SCIM, a two-factor policy, roles scoped to the entity, and every decision recorded. The security questionnaire answers the rest. Administration → Workflow & approvals; Identity & provisioning. In part
Relationship management Stakeholders engaged and heard. Customers and partners answer assessments without a seat; requesters rate each resolved request. Assessments; the portal. In part
Strategy management Direction set and cascaded. Factors and objectives per part of the organisation, with KPIs and targets, rolled up the hierarchy; PI objectives tied to factors where SAFe runs. Strategic planning. In part
Architecture management Dependencies between services understood. Services record what they depend on and are part of; collisions are read one dependency away. No architecture beyond that. Delivery → Services. In part
Supplier management, workforce and talent management — Not addressed. The calendar's who is away is for scheduling, not workforce management. — No

Technical management practices

Practice ITIL 4 asks for DilliC does Where Status
Software development and management Code changes traceable to the work and the authorisation. Commits and pull requests are tied to the work item they cite; a branch can be created from an item; a merge can take the item's next step; what an AI coding assistant was asked and answered is written on the item's changelog. Administration → Connections → Version control & CI; the Terminal tab; chapter 21. Yes
Infrastructure and platform management — Environments are named and ordered, and that is all. Administration → Environments. In part

4. What the organisation supplies by procedure

Where a row above says In part or No, the organisation covers the gap outside the tool. An auditor should ask for these alongside the DilliC evidence.

  • Change models and standard-change catalogue. Which kinds of change are standard, and the rehearsed procedure for each, kept as Pages. The change type on each record is the person's judgement, not a lookup.
  • Emergency change procedure. Who may authorise an emergency change, and how a change authorised after it went out is reviewed. DilliC records that it was not authorised in advance; the procedure says what follows.
  • Change communication. How users of a service are told of a change window. DilliC warns the approvers and the pipeline, not the users.
  • Test evidence. Where test results live. DilliC holds the test plan and whether the change reached a test environment, not the results.
  • Monitoring. Which system detects outages, and how an outage becomes an incident on the desk.
  • The CMDB beyond services. Where hardware, licences and detailed configuration are kept, if the organisation needs them.
  • Service levels as agreements. The signed SLA, where a customer holds one; DilliC holds the promises and measures them.

5. The auditor's walk through a live account

Each line is a thing to look at in a running account, with what should be there. An hour is enough. Where a line fails, the organisation has either not configured DilliC that way or is not using the control; either is a finding.

Policy

  • Administration → Modules: Change management and Approvals are on, and Service desk if incidents are claimed.
  • Administration → Workflow & approvals → Change enablement: the workflow has an assessment status, an authority status that a gated move leaves, an implementation status, a review status and a closed status, each mapped to one of the seven states.
  • Risk assessment: the questions in use, each marked risk or impact, with the safe answer first and a score on each answer. Note whether the seven shipped questions were kept or rewritten.
  • Which authority, by risk: a rule for each risk level, and any rule by type. Note which, if any, route to no gate, and whether Emergency has a rule of its own.
  • Approval gates: the Change Advisory Board gate, or its equivalent: who decides, how many approvals, and that the author may not approve.
  • Administration → Environments: the production environment is marked, and its authorisation is Recorded or Gated. Note which.
  • Administration → Connections → Version control & CI: a pipeline is connected and reports deployments; the webhook secret has been rotated within the period the organisation's policy sets.

Records

  • Delivery → Release path → Change requests: pick three closed changes, one of each type if the organisation has them. On each: implementation, rollback and test plans are filled; the services touched are named; the assessment is answered and the levels match the score or carry a named override.
  • On each: the event history shows raised, assessed, submitted, authorised, implemented and reviewed, with actors and times in order; the approval decisions name the deciders and their comments, and none is the requester.
  • On each: planned and actual windows are both present; where they differ, the difference is explained in the review notes.
  • On each: an outcome is recorded. For a failed or rolled back outcome, an incident or problem is linked under Consequences.
  • Pick one change still open: confirm it cannot be submitted with unfinished work, by trying.
  • Delivery → Calendar: a freeze exists for the period the organisation says it froze; a change inside it carries the warning; the approver's note on that change acknowledges it.
  • Delivery → Release path → Deployments, filtered to production: no arrival is flagged as unauthorised or bypassed, or each that is has a change authorising it after the fact and a review that says so.
  • Delivery → Services: the critical services each have an owner, a criticality and their dependencies, and the needs realigning filter is empty or explained.

Measurement

  • Reports → Change requests, 90 days: success rate, change failure rate, emergency share and median lead time are present, and the organisation can say what it does when they move.
  • A service's page: the twelve-month health figures are populated, and a month ringed as delivered here can be matched to a closed change.
  • Reports → Service desk: the reply and resolve promises and how often they were kept, if the desk is claimed.

Integrity

  • Administration → Data: export the account. Confirm the export carries the change requests, their events and the approval decisions, so the record outlives the subscription.
  • Ask whether any audit row has ever been edited or deleted. The answer, from DilliC's side, is that none can be: the terms say so, and an erasure request anonymises a person's name while keeping the act.

6. Keeping this map true

The map describes the product on the date above. The questionnaire's control CCC, "Does the product support the customer's own change management?", makes the same claims in fewer words, and this document should be read against it and against the user guide's chapters 9, 17 and 21 when any of them changes. A row that no longer matches the product is a defect in this document, and we would like to hear of it at support@dillic.app.

This is the same document the hosted service serves from its trust page, read from the release that is running. All documents.